Duke-962978
20 MW generation in Greenwood, SC · In queue since September 2024
20 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-962978 is a proposed 20 MW solar generation project located in Greenwood County, South Carolina. The project is being developed by Duke and is interconnected to the Duke Energy Carolinas system. It entered the interconnection queue on September 27, 2024, and is currently in the Cluster Study phase of the interconnection process.
The proposed project consists of 20 MW of solar photovoltaic generation capacity. It is listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
SC
County
Greenwood
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-962978