Duke-962982
60 MW generation in Laurens, SC · In queue since September 2024
60 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-962982 is a proposed 60 MW solar generation project located in Laurens County, South Carolina. The project is being developed by Duke Energy Carolinas and consists of 60 MW of solar photovoltaic generation. It is currently listed as active in the Duke Energy Carolinas interconnection queue with an entry date of September 27, 2024.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection is the CLINTON BL 100kV substation.
Generated from interconnection queue and public data sources
State
SC
County
Laurens
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
CLINTON BL 100kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-962982