Duke-963118
35 MW generation in Anderson, SC · In queue since September 2024
35 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-963118 is a proposed 35 MW solar generation project located in Anderson County, South Carolina. The project, developed by Duke, is interconnected to the Duke Energy Carolinas queue with an entry date of September 27, 2024. Its interconnection status is currently in the Cluster Study phase.
The proposed project consists of 35 MW of solar photovoltaic generation capacity. It is listed as an active project within the interconnection queue.
Generated from interconnection queue and public data sources
State
SC
County
Anderson
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-963118