Duke-963467
68 MW generation in Chester, SC · In queue since September 2024
68 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-963467 is a proposed 68 MW solar generation project located in Chester County, South Carolina. The project is being developed by Duke and has an interconnection queue entry date of September 30, 2024, with Duke Energy Carolinas. Its interconnection status is currently in the Cluster Study phase within the Duke Energy Carolinas queue.
The proposed project, which appeared in recent news coverage, consists of 68 MW of solar photovoltaic generation. The point of interconnection is the PARR WH 100kV substation.
Generated from interconnection queue and public data sources
State
SC
County
Chester
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Service Type
—
Point of Interconnection
PARR WH 100kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-963467