Project Duke-963469 — Project Summary

Queue ID
Duke-963469
Capacity
28.75 MW
Technology
Solar
Status
active
Location
Davidson, NC
Region
Southeast
Developer
IA Status
Cluster Study

Duke-963469

Duke-963469BetaActiveSolarDukeLBNL

28.75 MW generation in Davidson, NC · In queue since September 2024

28.75 MW

Capacity

1

Components

Solar

1y 8m

In Queue

Cluster Study

IA Status

Interconnection

Total Duration

1y 8m

Impact Study25%
Queue EntrySep 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

Duke-963469 is a proposed solar generation project with a total capacity of 28.75 MW. The project is located in Davidson County, North Carolina, within the Duke Energy Carolinas service area. Duke is the listed entity for the project, which consists of 28.75 MW of solar photovoltaic generation.

The project is currently in the Duke Energy Carolinas interconnection queue with a queue entry date of September 30, 2024. Its interconnection status is listed as "Cluster Study". The point of interconnection is the LEXINGTON N 100kV substation.

Generated from interconnection queue and public data sources

Project Details

State

NC

County

Davidson

Grid Region

Southeast

Market

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Service Type

Point of Interconnection

LEXINGTON N 100kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Duke Carolinas
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project Duke-963469