Duke-963472
70 MW generation in Robeson, NC · In queue since September 2024
70 MW
Capacity
1
Components
Solar
1y 8m
In Queue
Cluster Study
IA Status
Total Duration
1y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Duke-963472 is a proposed 70 MW solar generation project located in Robeson County, North Carolina. The project is being developed by Duke and has an interconnection point at the Weatherspoon Plant - Fayetteville 230kV. It is listed as active in the Duke Energy Progress interconnection queue with an entry date of September 30, 2024. The project's interconnection status is currently in the Cluster Study phase.
The proposed project consists of 70 MW of solar photovoltaic generation. It is located in the Southeast region.
Generated from interconnection queue and public data sources
State
NC
County
Robeson
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Weatherspoon Plant - Fayetteville 230kV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.