Duke-98
14 MW generation in Liberty, FL · In queue since February 2009 · Proposed COD June 2009
14 MW
Capacity
1
Components
Other
17y 3m
In Queue
IA Executed
IA Status
COD target: 2009
Total Duration
4 months
Schedule
206 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2009-06-01
Duke-98 is a proposed 14 MW generation project located in Liberty County, Florida. The project, developed by Telogia Biomass, utilizes an "Other" technology type. It is interconnected with Duke Energy Florida via the Liberty Substation.
The project is listed in the Duke interconnection queue as "Duke-98," with a queue entry date of February 10, 2009. The proposed commercial operation date was June 1, 2009. The project's interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
FL
County
Liberty
Grid Region
Southeast
Market
—
Developer
Telogia Biomass
Utility
Duke Energy Florida
Entity
Duke
Service Type
—
Point of Interconnection
Liberty Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-98