Duke-PP00001
75 MW generation in Darlington, SC · In queue since September 2024 · Proposed COD March 2027
75 MW
Capacity
1
Components
Solar
1y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
2y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-31
Duke-PP00001 is a proposed 75 MW solar generation project located in Darlington County, South Carolina. The project, developed by Duke, is interconnected within the Duke Energy Progress queue with an entry date of September 1, 2024, and a proposed commercial operation date of March 31, 2027. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is linked to the existing Robinson Plant in Florence, South Carolina, as indicated by its Point of Interconnection. The project has appeared in recent news coverage regarding Duke Energy's renewable energy initiatives.
Generated from interconnection queue and public data sources
State
SC
County
Darlington
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Robinson Plant - Florence
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-PP00001