Duke-PP00007
75 MW generation in Darlington, SC · In queue since December 2024 · Proposed COD July 2027
75 MW
Capacity
1
Components
Solar
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-14
Duke-PP00007 is a proposed 75 MW solar generation project located in Darlington County, South Carolina. The project, developed by Duke, is interconnected to the Duke Energy Progress system. It entered the interconnection queue on December 6, 2024, with a proposed commercial operation date of July 14, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project is linked to the existing Robinson Plant - Rockingham. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
SC
County
Darlington
Grid Region
Southeast
Market
—
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Service Type
—
Point of Interconnection
Robinson Plant - Rockingham
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Duke Carolinas
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project Duke-PP00007