AC120SB Project
120 MW hybrid in Otero, NM · In queue since September 2017 · Proposed COD June 2022
120 MW
Capacity
1
Components
Solar
8y 8m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
4y 9m
Schedule
48 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2022-06-05
The AC120SB Project is a proposed 120 MW hybrid solar and battery energy storage project located in Otero County, New Mexico. The development project consists of 120 MW of solar generation capacity. It is interconnected to the El Paso Electric Company (EPE) via the Otero 345kV Substation.
The project is listed in the El Paso Electric (EPE) interconnection queue as queue ID EPE-LG-17-9-3, with an interconnection queue entry date of September 27, 2017. The proposed commercial operation date is June 5, 2022, and the Interconnection Agreement (IA) has been executed. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NM
County
Otero
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
—
Point of Interconnection
Otero 345kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN