CO100SB Project
100 MW hybrid in Otero, NM · In queue since March 2019 · Proposed COD April 2027
100 MW
Capacity
1
Components
Solar
7y 2m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-04-01
The CO100SB Project is a proposed 100 MW hybrid solar and battery energy project located in Otero County, New Mexico. The project, under development by El Paso Electric Company (EPE), consists of 100 MW of solar generation capacity. It is interconnected to the El Paso Electric Company queue as project EPE-LG-19-3-4, with an initial queue entry date of March 27, 2019. The proposed commercial operation date is April 1, 2027.
The project's interconnection point is the Chaparral-Oro Grande 115KV Line. The interconnection agreement (IA) for the project has been executed. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
NM
County
Otero
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
—
Point of Interconnection
Chaparral-Oro Grande 115KV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CO100SB Project