LA300W
300 MW generation in Luna, NM · In queue since March 2022 · Proposed COD December 2028
300 MW
Capacity
1
Components
Wind
4y 2m
In Queue
Suspended
IA Status
COD target: 2028
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-15
The LA300W project is a proposed 300 MW wind generation project located in Luna County, New Mexico. The developer is El Paso Electric Company (EPE). It is listed in the El Paso Electric (EPE-LG) interconnection queue as entry EPE-LG 22-3-6, with a queue entry date of March 31, 2022. The proposed commercial operation date is December 15, 2028. The interconnection agreement status is currently suspended.
The project is to interconnect at the Luna-Afton 345kV point of interconnection. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
NM
County
Luna
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
—
Point of Interconnection
Luna-Afton 345kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.