VS75SB
75 MW hybrid in Dona Ana, NM · In queue since September 2022 · Proposed COD December 2026
75 MW
Capacity
1
Components
Solar
3y 8m
In Queue
IA Pending
IA Status
COD target: 2026
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
The VS75SB project is a proposed 75 MW hybrid solar and battery energy storage project located in Dona Ana County, New Mexico. The project consists of 75 MW of solar generation. It is in the El Paso Electric Company (EPE) interconnection queue as project EPE-LG-22-9-7, with a queue entry date of September 30, 2022, and a proposed commercial operation date of December 1, 2026. Its interconnection agreement (IA) status is currently listed as "IA Pending".
The project would interconnect to the Salopek-Vado 115kV line. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
NM
County
Dona Ana
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
—
Point of Interconnection
Salopek-Vado 115kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about VS75SB