Sf250SB
250 MW hybrid in Hudspeth, TX · In queue since September 2023 · Proposed COD December 2028
250 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
The Sf250SB project is a proposed 250 MW hybrid solar and battery energy storage development in Hudspeth County, Texas. The project consists of 250 MW of solar generation. It is located in the West region and is being proposed within the El Paso Electric Company (EPE) service area.
The project, identified as queue ID EPE-LG-23-9-4, entered the El Paso Electric interconnection queue on September 29, 2023, with a proposed commercial operation date of December 31, 2028. The interconnection request is currently in the Facility Study phase and the point of interconnection is the San Felipe 115kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TX
County
Hudspeth
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
—
Point of Interconnection
San Felipe 115kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Sf250SB