Sf150SB
150 MW hybrid in El Paso, TX · In queue since March 2024 · Proposed COD May 2027
150 MW
Capacity
1
Components
Solar
2y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
The Sf150SB project is a proposed 150 MW hybrid solar and battery energy storage development in El Paso County, Texas. The project consists of 150 MW of solar generation. It is located in the West region and is being proposed within the El Paso Electric Company (EPE) service area.
The project, identified as EPE-LG-24-3-13 in the EPE interconnection queue, entered the queue on March 28, 2024, with a proposed commercial operation date of May 1, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the San Felipe 115kV Substation.
Generated from interconnection queue and public data sources
State
TX
County
El Paso
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
—
Point of Interconnection
San Felipe 115kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.