Ne100S
100 MW generation in El Paso, TX · In queue since March 2024 · Proposed COD February 2027
100 MW
Capacity
1
Components
Solar
2y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-15
The Ne100S project is a proposed 100 MW solar generation project located in El Paso County, Texas. The project is interconnected to the El Paso Electric Company (EPE) grid.
The project, identified as EPE-LG-24-3-8 in the EPE interconnection queue, entered the queue on March 27, 2024, with a proposed commercial operation date of February 15, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is Newman 115kV or an alternate POI.
Generated from interconnection queue and public data sources
State
TX
County
El Paso
Grid Region
Mountain West
Market
—
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Service Type
—
Point of Interconnection
Newman 115kV or Alternate POI
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.