Grandview 5 W
249 MW generation in Gray, TX · In queue since July 2006
249 MW
Capacity
1
Components
Wind
19y 10m
In Queue
Facility Study
IA Status
Total Duration
19y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The Grandview 5 W project is a proposed 249 MW wind generation project located in Gray County, Texas. The project, developed by Eon, is interconnected within the ERCOT region and entered the ERCOT interconnection queue as ERCOT-08INR0019b on July 21, 2006. Its interconnection status is currently in the Facility Study phase.
The proposed project consists of 249 MW of wind generation capacity. The project's queue status is currently listed as suspended.
Generated from interconnection queue and public data sources
State
TX
County
Gray
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Eon
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
79005 Railhead 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Railhead Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.