Harald (BearKat Wind B)
162.1 MW generation in Glasscock, TX · In queue since November 2013 · Proposed COD April 2026
162.1 MW
Capacity
1
Components
Wind
12y 6m
In Queue
IA Executed
IA Status
Signed May 2018
Queue → IA
4y 6m
IA → COD
7y 11m
Total Duration
4y 6m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-04-30
The Harald (BearKat Wind B) project is a proposed 162.1 MW wind generation project located in Glasscock County, Texas. The developer is CIP. It is interconnected within the ERCOT region under queue ID ERCOT-15INR0064b, with an interconnection queue entry date of November 27, 2013. The proposed commercial operation date is April 30, 2026.
The project's interconnection agreement (IA) was executed on May 30, 2018. The point of interconnection is the 59903 Bearkat 345kV substation. The Harald (BearKat Wind B) project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Glasscock
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
CIP
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59903 Bearkat 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Bearkat Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26