Stella 2 Wind
201 MW generation in Kenedy, TX · In queue since June 2013
201 MW
Capacity
1
Components
Wind
12y 11m
In Queue
Facility Study
IA Status
Total Duration
12y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Stella 2 Wind is a proposed 201 MW wind generation project located in Kenedy County, Texas. The developer is Eon. This project is listed in the ERCOT interconnection queue as entry ERCOT-16INR0012, with a queue entry date of June 13, 2013. Its interconnection status is currently in the Facility Study phase. The point of interconnection is at the tap 345kV 80076 Ajo - 80071 Zorillo.
The proposed project is linked to the existing Stella Wind Farm operating plant (EIA plant ID 59063). Recent news coverage has discussed deals, development, and grid aspects of the project.
Generated from interconnection queue and public data sources
State
TX
County
Kenedy
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Eon
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 80076 Ajo - 80071 Zorillo
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- STELLA_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26