Big Sampson Wind
265.4 MW generation in Crockett, TX · In queue since May 2015 · Proposed COD March 2026
265.4 MW
Capacity
1
Components
Wind
11 years
In Queue
IA Executed
IA Status
Signed Nov 2019
Queue → IA
4y 6m
IA → COD
6y 4m
Total Duration
4y 6m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-03-31
Big Sampson Wind is a proposed 265.4 MW wind generation project located in Crockett County, Texas. The developer is Big Sampson Wind Project, LLC. The project is interconnected to the ERCOT grid under queue ID ERCOT-16INR0104, with an interconnection queue entry date of May 11, 2015. The proposed commercial operation date is March 31, 2026, and the Interconnection Agreement (IA) was executed on November 8, 2019. The point of interconnection is tap 345kV 76015 Cedar Canyon - 7053 Noelke.
The proposed project is linked to the existing, operating Big Sampson Wind plant (EIA plant ID 68873). The project has been the subject of recent news coverage, with eight articles related to deals, industry, and development.
Generated from interconnection queue and public data sources
State
TX
County
Crockett
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Big Sampson Wind Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 76015 Cedar Canyon - 7053 Noelke
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
- POI Substation
- Iraan Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Big Sampson Wind