Loma Pinta Wind (ERCOT-16INR0112) — Project Summary

Queue ID
ERCOT-16INR0112
Capacity
197.01 MW
Technology
Wind
Status
active
Location
La Salle, TX
Region
ERCOT
Developer
Enerverse
IA Status
IA Executed

Loma Pinta Wind

ERCOT-16INR0112BetaActiveWindERCOTLBNL + Live

197.01 MW generation in La Salle, TX · In queue since May 2015 · Proposed COD December 2026

197.01 MW

Capacity

1

Components

Wind

11 years

In Queue

IA Executed

IA Status

Signed Dec 2017

Interconnection

Queue → IA

2y 7m

IA → COD

9 years

Total Duration

2y 7m

Construction75%
Queue EntryMay 18, 2015

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 13, 2017

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-12-31

About

The Loma Pinta Wind project is a proposed 197.01 MW wind generation facility in La Salle County, Texas. The project, developed by Enerverse, is currently active in the ERCOT interconnection queue as entry ERCOT-16INR0112, with a queue entry date of May 18, 2015. The proposed commercial operation date is December 31, 2026.

The project has an executed Interconnection Agreement (IA), which was finalized on December 13, 2017. The Point of Interconnection (POI) is the 5705 Fowlerton 138kV substation. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

La Salle

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Enerverse

Utility

Entity

ERCOT

Service Type

Point of Interconnection

5705 Fowlerton 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Fowlerton Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Loma Pinta Wind