Wake Solar
150 MW generation in Crosby, TX · In queue since July 2015
150 MW
Capacity
1
Components
Solar
10y 10m
In Queue
Facility Study
IA Status
Total Duration
10y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Wake Solar is a proposed 150 MW solar generation project located in Crosby County, Texas. The project, developed by Invenergy, entered the ERCOT interconnection queue as entry ERCOT-16INR0119 on July 20, 2015. Its interconnection status is currently in the Facility Study phase.
The project's status is listed as suspended. Wake Solar has been the subject of recent news coverage, with six articles appearing in industry, regulatory, and deals publications.
Generated from interconnection queue and public data sources
State
TX
County
Crosby
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Invenergy
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59904 Cottonwood 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Cottonwood Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26