FGE Texas 2 Gas (ERCOT-17INR0010) — Project Summary

Queue ID
ERCOT-17INR0010
Capacity
742.9 MW
Technology
Gas
Status
suspended
Location
Mitchell, TX
Region
ERCOT
Developer
IA Status

FGE Texas 2 Gas

ERCOT-17INR0010BetaSuspendedGasERCOTLBNL

742.9 MW generation in Mitchell, TX

742.9 MW

Capacity

1

Components

Gas

In Queue

IA Status

Status
Latest activityDelay announcedUpstream Online · 2025-11-13
Expected COD2027Upstream Online · 2025-11-13
Interconnection
Suspended0%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

The FGE Texas 2 Gas project is a proposed 742.9 MW natural gas generation project located in Mitchell County, Texas. The project is listed in the ERCOT interconnection queue as entry ERCOT-17INR0010. Its status is currently suspended.

The proposed project has appeared in recent industry news.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Mitchell

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Utility

Entity

ERCOT

Service Type

Data Source

LBNL

DeveloperChevronUpstream Online · 2025-11-13
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles