Coyote Wind (ERCOT-17INR0027b) — Project Summary

Queue ID
ERCOT-17INR0027b
Capacity
242.6 MW
Technology
Wind
Status
active
Location
Scurry, TX
Region
ERCOT
Developer
Coyote Wind
IA Status
IA Executed

Coyote Wind

ERCOT-17INR0027bBetaActiveWindERCOTLBNL + Live

242.6 MW generation in Scurry, TX · In queue since April 2015 · Proposed COD December 2025

242.6 MW

Capacity

1

Components

Wind

11y 1m

In Queue

IA Executed

IA Status

Signed Aug 2016

Status
as of 7y 1m ago
Latest milestoneturbine supply contract awardedWindpower Engineering & Development · 2019-04-25
Expected CODQ4 2020Windpower Engineering & Development · 2019-04-25
Interconnection

Queue → IA

1y 4m

IA → COD

9y 4m

Total Duration

1y 4m

Schedule

5 months past proposed COD

Construction75%
Queue EntryApr 22, 2015

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 9, 2016

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2025-12-01

About

The Coyote Wind project is a proposed wind generation facility with a total capacity of 242.6 MW, located in Scurry County, Texas. The developer is listed as Coyote Wind. The project is in the ERCOT interconnection queue as entry ERCOT-17INR0027b, with a queue entry date of April 22, 2015, and a proposed commercial operation date of December 1, 2025. The interconnection agreement (IA) has been executed as of August 9, 2016.

The proposed project is linked to the existing Coyote Wind LLC operating plant (EIA plant ID 63655). The Coyote Wind project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Scurry

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Coyote Wind

Utility

Entity

ERCOT

Service Type

Point of Interconnection

11305 Dermott 345kV

Data Source

LBNL + Live

DeveloperEDF Renewables North AmericaWindpower Engineering & Development · 2019-04-25
EPC contractorSiemens Gamesa Renewable EnergyWindpower Engineering & Development · 2019-04-25
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
HIGH
Nearest Node (Estimated)
DERMOTT_ALL

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.