Canyon Wind
308.82 MW generation in Scurry, TX · In queue since May 2016 · Proposed COD February 2025
308.82 MW
Capacity
1
Components
Wind
10 years
In Queue
IA Executed
IA Status
Signed Sep 2018
Queue → IA
2y 4m
IA → COD
6y 5m
Total Duration
2y 4m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-02-28
Canyon Wind is a proposed wind generation project with a total capacity of 308.82 MW. The project, developed by Canyon Wind Energy, LLC, is located in Scurry County, Texas, within the ERCOT region. It is listed in the ERCOT interconnection queue as entry 18INR0030, with an original queue entry date of May 9, 2016. The proposed commercial operation date is February 28, 2025. An Interconnection Agreement (IA) has been executed for the project, with an IA date of September 20, 2018.
The proposed project is linked to the existing Canyon Wind Project, LLC operating plant (EIA plant ID 60271). Recent news coverage of the project includes 24 articles related to industry, regulatory, grid, and hazard topics.
Generated from interconnection queue and public data sources
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Canyon Wind Energy, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
11319 SCOSW ScurryCounty 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CANYONWD_ALL
- POI Substation
- Scurry Substation