Maryneal Wind
182.4 MW generation in Nolan, TX · In queue since May 2016 · Proposed COD July 2025
182.4 MW
Capacity
1
Components
Wind
10 years
In Queue
IA Executed
IA Status
Signed Jan 2020
Queue → IA
3y 8m
IA → COD
5y 6m
Total Duration
3y 8m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-07-31
The Maryneal Wind project is a proposed 182.4 MW wind generation facility in Nolan County, Texas. Developed by Maryneal Windpower, LLC, the project consists entirely of wind generation. It is listed in the ERCOT interconnection queue as entry ERCOT-18INR0031, with a queue entry date of May 26, 2016, and a proposed commercial operation date of July 31, 2025. The project's interconnection agreement (IA) was executed on January 31, 2020.
The proposed project is linked to the existing Maryneal Windpower operating plant (EIA plant ID 62836). Recent news coverage has discussed the project, with articles focusing on industry trends and development updates.
Generated from interconnection queue and public data sources
State
TX
County
Nolan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Maryneal Windpower, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
71050 Bitter Creek 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SWTWN4_WND45
- POI Substation
- Sweetwater Wind 5 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26