Sweetwater 1 repower (ERCOT-18INR0073) — Project Summary

Queue ID
ERCOT-18INR0073
Capacity
3 MW
Technology
Wind
Status
active
Location
Nolan, TX
Region
ERCOT
Developer
Leeward Energy
IA Status
IA Executed

Sweetwater 1 repower

ERCOT-18INR0073BetaActiveWindERCOTLBNL + Live

3 MW generation in Nolan, TX · In queue since February 2018 · Proposed COD November 2024

3 MW

Capacity

1

Components

Wind

8y 3m

In Queue

IA Executed

IA Status

Signed Oct 2002

Interconnection

IA → COD

22y 1m

Total Duration

8y 3m

Schedule

17 months past proposed COD

Construction75%
Queue EntryFeb 9, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 23, 2002

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2024-11-30

About

The Sweetwater 1 repower project is a proposed 3 MW wind generation project located in Nolan County, Texas. The developer is Leeward Energy. It is interconnected within the ERCOT region under queue ID ERCOT-18INR0073. The project entered the interconnection queue on February 9, 2018, with a proposed commercial operation date of November 30, 2024.

The interconnection agreement for the Sweetwater 1 repower project was executed on October 23, 2002. The point of interconnection is the 71050 Bitter Creek 345kV. The project is currently listed as active in the interconnection queue. The project has appeared in recent news.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Nolan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Leeward Energy

Utility

Entity

ERCOT

Service Type

Point of Interconnection

71050 Bitter Creek 345kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Bitter Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.