Monte Alto 2 Wind (ERCOT-19INR0023) — Project Summary

Queue ID
ERCOT-19INR0023
Capacity
307.9 MW
Technology
Wind
Status
active
Location
Willacy, TX
Region
ERCOT
Developer
Terra-Gen
IA Status
IA Executed

Monte Alto 2 Wind

ERCOT-19INR0023BetaActiveWindERCOTLBNL + Live

307.9 MW generation in Willacy, TX · In queue since November 2016 · Proposed COD June 2027

307.9 MW

Capacity

1

Components

Wind

9y 6m

In Queue

IA Executed

IA Status

Signed Mar 2022

Interconnection

Queue → IA

5y 4m

IA → COD

5y 3m

Total Duration

5y 4m

Construction75%
Queue EntryNov 4, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMar 22, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2027-06-01

About

The Monte Alto 2 Wind project is a proposed wind generation project with a total capacity of 307.9 MW. Located in Willacy County, Texas, the project is being developed by Terra-Gen. It is interconnected within the ERCOT region and entered the ERCOT interconnection queue as queue ID ERCOT-19INR0023 on November 4, 2016.

The proposed commercial operation date for the project is June 1, 2027. An Interconnection Agreement (IA) for the project was executed on March 22, 2022. The Point of Interconnection (POI) is at the tap 345kV 8318 Rio Hondo - 8383 N Edinburg. The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Willacy

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Terra-Gen

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 8318 Rio Hondo - 8383 N Edinburg

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
MEDIUM
POI Substation
Rio Hondo Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.