Norton Solar
128.48 MW generation in Runnels, TX · In queue since March 2017 · Proposed COD November 2025
128.48 MW
Capacity
1
Components
Solar
9y 2m
In Queue
IA Executed
IA Status
Signed Jun 2019
Queue → IA
2y 3m
IA → COD
6y 5m
Total Duration
2y 3m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-11-24
The Norton Solar project is a proposed 128.48 MW solar generation facility in Runnels County, Texas. Developed by TAI Norton Solar, LLC, the project consists of 128.48 MW of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-19INR0035, with a queue entry date of March 6, 2017, and a proposed commercial operation date of November 24, 2025. The project's Interconnection Agreement (IA) was executed on June 20, 2019.
The proposed project is linked to the existing Norton Solar Farm operating plant (EIA ID 61967). It has appeared in recent news coverage related to development and deals.
Generated from interconnection queue and public data sources
State
TX
County
Runnels
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
TAI Norton Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60451 Garnet 138kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
- POI Substation
- Colorado River Municipal Water District #2 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26