Long Point Solar (ERCOT-19INR0042) — Project Summary

Queue ID
ERCOT-19INR0042
Capacity
120 MW
Technology
Solar
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Long Point Solar, LLC
IA Status
IA Executed

Long Point Solar

ERCOT-19INR0042BetaActiveSolarERCOTLBNL + Live

120 MW generation in Brazoria, TX · In queue since March 2017 · Proposed COD April 2026

120 MW

Capacity

1

Components

Solar

9y 2m

In Queue

IA Executed

IA Status

Signed Oct 2019

Interconnection

Queue → IA

2y 7m

IA → COD

6y 6m

Total Duration

2y 7m

Schedule

1 months past proposed COD

Construction75%
Queue EntryMar 15, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 24, 2019

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-04-07

About

Long Point Solar is a proposed 120 MW solar generation project in Brazoria County, Texas. Developed by Long Point Solar, LLC, the project consists of 120 MW of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-19INR0042, with a queue entry date of March 15, 2017, and a proposed commercial operation date of April 7, 2026. The project's Interconnection Agreement (IA) was executed on October 24, 2019.

The proposed project is linked to the existing Long Point Solar operating plant (EIA ID 68998). Recent news coverage indicates activity related to the project, with 13 articles categorized as deals, industry, regulatory, grid, and development.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Long Point Solar, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

138 KV (CEHE Sub) Tap Burke (42410) - Eagle Nest (42430) ckt 02

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
HIGH
Nearest Node (Estimated)
RN_LNP_SLR

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Long Point Solar