301.1 MW generation in Brown, TX · In queue since June 2017 · Proposed COD February 2027
301.1 MW
Capacity
1
Components
Solar
8y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
9y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-02-20
Horseshoe Bend Solar is a proposed 301.1 MW solar generation project located in Brown County, Texas. The project, developed by Clenera, is in the ERCOT interconnection queue as entry ERCOT-19INR0075, with a queue entry date of June 23, 2017. Its proposed commercial operation date is February 20, 2027, and its interconnection status is currently in the Facility Study phase.
The Horseshoe Bend Solar project has been the subject of recent news coverage, with three articles categorized as relating to deals and industry developments.
Generated from interconnection queue and public data sources
State
TX
County
Brown
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Clenera
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1444 Brown 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BBSES_UNIT1
- POI Substation
- Big Brown Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.