Whitehorse Wind
418.9 MW generation in Fisher, TX · In queue since June 2017 · Proposed COD December 2026
418.9 MW
Capacity
1
Components
Wind
8y 11m
In Queue
IA Executed
IA Status
Signed Dec 2018
Queue → IA
1y 6m
IA → COD
8 years
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-31
The Whitehorse Wind project is a proposed 418.9 MW wind generation facility in Fisher County, Texas. The project, developed by MESQUITE STAR SPECIAL LLC, is located within the ERCOT region and interconnected at the 68001 Clayton 345kV point of interconnection.
The project entered the ERCOT interconnection queue as entry ERCOT-19INR0080 on June 23, 2017, with a proposed commercial operation date of December 31, 2026. An Interconnection Agreement (IA) for the project was executed on December 5, 2018, and the project is currently listed as active in the queue.
Generated from interconnection queue and public data sources
State
TX
County
Fisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
MESQUITE STAR SPECIAL LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68001 Clayton 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Clayton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.