Tehuacana Wind
600 MW generation in Limestone, TX
600 MW
Capacity
1
Components
Wind
—
In Queue
—
IA Status
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Tehuacana Wind project is a 600 MW wind generation facility located in Limestone County, Texas. The project is listed in the ERCOT interconnection queue as entry 19INR0101.
The Tehuacana Wind project's interconnection status is currently suspended. The project has been the subject of recent news coverage, with 18 articles related to the grid and industry.
Generated from interconnection queue and public data sources
State
TX
County
Limestone
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.