Rodeo Solar
200 MW generation in Andrews, TX · In queue since June 2017 · Proposed COD November 2026
200 MW
Capacity
1
Components
Solar
8y 11m
In Queue
IA Executed
IA Status
Signed Aug 2019
Queue → IA
2y 2m
IA → COD
7y 3m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-11-30
Rodeo Solar is a proposed 200 MW solar generation project located in Andrews County, Texas. The developer is Core Solar SPV I, LLC. The project is in the ERCOT interconnection queue as entry ERCOT-19INR0103, with a queue entry date of June 29, 2017, and a proposed commercial operation date of November 30, 2026.
The project's Interconnection Agreement (IA) was executed on August 20, 2019. The point of interconnection is the 138kV 11273 NELSON SWITCH. Rodeo Solar has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Andrews
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Core Solar SPV I, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
138kV 11273 NELSON SWITCH
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Rodeo Solar