Azalea Springs Solar
181 MW generation in Angelina, TX · In queue since July 2017 · Proposed COD October 2025
181 MW
Capacity
1
Components
Solar
8y 10m
In Queue
IA Executed
IA Status
Signed Sep 2023
Queue → IA
6y 2m
IA → COD
2y 1m
Total Duration
6y 2m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-10-31
The Azalea Springs Solar project is a proposed 181 MW solar generation project located in Angelina County, Texas. The developer is AZALEA SPRINGS SOLAR PARK LLC. This project is in the ERCOT interconnection queue as entry ERCOT-19INR0110, with a queue entry date of July 26, 2017, and a proposed commercial operation date of October 31, 2025. The project's interconnection agreement was executed on September 14, 2023.
The proposed project is linked to the existing Azalea Springs Solar Park operating plant (EIA ID 68470). Recent news coverage has discussed the project in the context of regulatory and industry developments.
Generated from interconnection queue and public data sources
State
TX
County
Angelina
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
AZALEA SPRINGS SOLAR PARK LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV Jim English _x0013_ Lufkin Chipper Mill
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Temple Inland Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.