Pierce Wind
300 MW generation in Wharton, TX
300 MW
Capacity
1
Components
Wind
—
In Queue
—
IA Status
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
The proposed Pierce Wind project is a 300 MW wind generation facility located in Wharton County, Texas. The project is in the ERCOT interconnection queue as entry ERCOT-19INR0161. Its status is currently listed as suspended.
The Pierce Wind project has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
—
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26