Shifting Gale Wind
289 MW generation in Castro, TX · In queue since April 2018 · Proposed COD December 2025
289 MW
Capacity
1
Components
Wind
8y 1m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
The proposed Shifting Gale Wind project is a 289 MW wind generation facility in Castro County, Texas. The project, developed by SEAWAY WIND ENERGY LLC, is located within the ERCOT region and interconnected at the 23912 Ogallala 345kV point of interconnection. It entered the ERCOT interconnection queue as project ERCOT-19INR0175 on April 26, 2018, with a proposed commercial operation date of December 31, 2025. The project's interconnection status is currently in the Facility Study phase, but is listed as suspended.
The Shifting Gale Wind project has been mentioned in recent news coverage pertaining to hazards.
Generated from interconnection queue and public data sources
State
TX
County
Castro
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
SEAWAY WIND ENERGY LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
23912 Ogallala 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Ogallala Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Shifting Gale Wind