Angelo Solar
195.41 MW generation in Tom Green, TX · In queue since November 2018 · Proposed COD October 2024
195.41 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
Signed Dec 2021
Queue → IA
3y 1m
IA → COD
2y 10m
Total Duration
3y 1m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2024-10-11
Angelo Solar is a proposed 195.41 MW solar generation project located in Tom Green County, Texas. The developer is ANGELO SOLAR LLC. The project is in the ERCOT interconnection queue as entry ERCOT-19INR0203, with a queue entry date of November 20, 2018, and a proposed commercial operation date of October 11, 2024. The Interconnection Agreement (IA) was executed on December 3, 2021.
The proposed project is linked to the existing Angelo Solar operating plant (EIA plant ID 68145). Recent news coverage of the project includes 13 articles related to industry, deals, the grid, and regulatory matters.
Generated from interconnection queue and public data sources
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
ANGELO SOLAR LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76009 Twin Buttes 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- ANG_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 5 articlesNo ask pi reports yet for this entity.
ask pi about Angelo Solar