Trinity Hills Wind repower
— generation in Young, TX · In queue since July 2017 · Proposed COD April 2026
—
Capacity
0
Components
8y 10m
In Queue
IA Executed
IA Status
Signed Oct 2018
Queue → IA
1y 3m
IA → COD
7y 6m
Total Duration
1y 3m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-04-01
The Trinity Hills Wind repower is a proposed wind generation project located in Young County, Texas. The project, with a total capacity not specified in available data, is being developed by Trinity Hills Wind Farm LLC. It is listed in the ERCOT interconnection queue as entry ERCOT-20INR0019, with a queue entry date of July 20, 2017, and a proposed commercial operation date of April 1, 2026.
The project has an executed Interconnection Agreement (IA), which was signed on October 17, 2018. The point of interconnection (POI) is the 17002 Garvey Rd 345kV substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Young
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Trinity Hills Wind Farm LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
17002 Garvey Rd 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.