WILDWIND
180.08 MW generation in Cooke, TX · In queue since October 2017 · Proposed COD April 2026
180.08 MW
Capacity
1
Components
Wind
8y 7m
In Queue
IA Executed
IA Status
Signed Feb 2020
Queue → IA
2y 4m
IA → COD
6y 2m
Total Duration
2y 4m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-04-15
The WILDWIND project is a proposed 180.08 MW wind generation project located in Cooke County, Texas. Developed by Wildcat Creek, the project consists of 180.08 MW of wind capacity. It is currently active in the ERCOT interconnection queue as entry ERCOT-20INR0033, with a queue entry date of October 18, 2017, and a proposed commercial operation date of April 15, 2026.
The project's Interconnection Agreement (IA) has been executed as of February 21, 2020. The point of interconnection (POI) is at the tap 345kV 1730 KrumW - 2373 Anna. The WILDWIND project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Cooke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Wildcat Creek
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1730 KrumW - 2373 Anna
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about WILDWIND