Baird North Wind
350 MW generation in Callahan, TX · In queue since May 2018 · Proposed COD December 2026
350 MW
Capacity
1
Components
Wind
8 years
In Queue
IA Executed
IA Status
Signed May 2019
Queue → IA
1 year
IA → COD
7y 7m
Total Duration
1 year
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-12-31
The Baird North Wind project is a proposed 350 MW wind generation facility in Callahan County, Texas. Developed by BMP Wind, LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-20INR0083, with a queue entry date of May 4, 2018. The proposed commercial operation date is December 31, 2026. An Interconnection Agreement (IA) was executed on May 31, 2019.
The project has been the subject of recent news coverage, with three articles categorized as industry news and deals. The point of interconnection is the 68008 Latimer 345kV location.
Generated from interconnection queue and public data sources
State
TX
County
Callahan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
BMP Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68008 Latimer 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Latimer Switchyard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.