Foxtrot Wind
268.2 MW generation in Bee, TX · In queue since July 2018 · Proposed COD March 2026
268.2 MW
Capacity
1
Components
Wind
7y 10m
In Queue
IA Executed
IA Status
Signed May 2020
Queue → IA
1y 10m
IA → COD
5y 10m
Total Duration
1y 10m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2026-03-31
Foxtrot Wind is a proposed wind generation project with a total capacity of 268.2 MW. The project, located in Bee County, Texas, is being developed by Lincoln Clean. It is interconnected within the ERCOT region under queue ID ERCOT-20INR0129, with an interconnection queue entry date of July 26, 2018. The project's proposed commercial operation date is March 31, 2026.
The interconnection agreement for Foxtrot Wind was executed on May 5, 2020. The point of interconnection is the AEP 88689 Tango 345kV station. The project is currently listed as active in the ERCOT interconnection queue.
Generated from interconnection queue and public data sources
State
TX
County
Bee
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Lincoln Clean
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
AEP 88689 Tango 345kV station
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.