Pine Forest Solar (ERCOT-20INR0203) — Project Summary

Queue ID
ERCOT-20INR0203
Capacity
301.51 MW
Technology
Solar
Status
active
Location
Hopkins, TX
Region
ERCOT
Developer
Pine Forest Solar I, LLC
IA Status
IA Executed

Pine Forest Solar

ERCOT-20INR0203BetaActiveSolarERCOTLBNL + Live

301.51 MW generation in Hopkins, TX · In queue since October 2018 · Proposed COD April 2026

301.51 MW

Capacity

1

Components

Solar

7y 7m

In Queue

IA Executed

IA Status

Signed Jul 2020

Status
as of 19 months ago
Latest milestoneconstruction start · 2024-10-02Wilson Sonsini · 2024-10-17
Interconnection

Queue → IA

1y 9m

IA → COD

5y 9m

Total Duration

1y 9m

Schedule

1 months past proposed COD

Construction75%
Queue EntryOct 4, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJul 29, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-04-01

About

Pine Forest Solar is a proposed 301.51 MW solar generation project located in Hopkins County, Texas. The developer is Pine Forest Solar I, LLC. The project is interconnected within the ERCOT region under queue ID ERCOT-20INR0203, with an interconnection queue entry date of October 4, 2018. The proposed commercial operation date is April 1, 2026, and the Interconnection Agreement was executed on July 29, 2020.

The project's point of interconnection is the Monticello Switch _x0013_ Allen Switch 345 kV Line. Pine Forest Solar has been the subject of recent news coverage, with seven articles categorized as development, regulatory, and deals.

Generated from interconnection queue and public data sources

Project Details

State

TX

County

Hopkins

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Pine Forest Solar I, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

Monticello Switch _x0013_ Allen Switch 345 kV Line

Data Source

LBNL + Live

DeveloperClearway Energy GroupIPE Real Assets · 2025-04-01
ApplicantPine Forest Solar LLC±Ksst Radio · 2022-12-12
AgencyHopkins County Commissioner Court±Ksst Radio · 2022-12-12
RulingApprovalKsst Radio · 2022-12-12
TransactionAcquisitionIPE Real Assets · 2025-04-01
Deal value$200.0MIPE Real Assets · 2025-04-01
OfftakerAIP ManagementIPE Real Assets · 2025-04-01
PPA structureVirtualIPE Real Assets · 2025-04-01
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (5)Beta

Last updated 2026-03-26

View all 5 articles