Signal Solar
51.79 MW generation in Hunt, TX · In queue since November 2018 · Proposed COD February 2025
51.79 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
Signed Oct 2020
Queue → IA
1y 11m
IA → COD
4y 4m
Total Duration
1y 11m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-02-24
Signal Solar is a proposed 51.79 MW solar generation project located in Hunt County, Texas. The developer is Adapture Renewables, Inc. The project is interconnected within the ERCOT region under queue ID ERCOT-20INR0208, with an interconnection queue entry date of November 7, 2018. The proposed commercial operation date is February 24, 2025. The Interconnection Agreement (IA) was executed on October 23, 2020.
The proposed project is linked to the existing BT Signal Ranch operating plant (EIA plant ID 67849). Signal Solar has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Hunt
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Adapture Renewables, Inc
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 6879 Wieland - 6883 Quinlan N
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SIG_SLR_RN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26