Hopkins Solar
320 MW generation in Hopkins, TX · In queue since November 2018
320 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
Signed Sep 2020
Queue → IA
1y 10m
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 12–24 months
Commercial operation date not yet determined
Hopkins Solar is a proposed 320 MW solar generation project located in Hopkins County, Texas. The project, developed by Hopkins Energy LLC, is interconnected within the ERCOT region under queue ID ERCOT-20INR0210. It entered the interconnection queue on November 20, 2018, and its interconnection agreement was executed on September 25, 2020. The project's status is currently suspended.
The proposed project is linked to the existing Hopkins Energy LLC operating plant (EIA plant ID 67424). Recent news coverage indicates regulatory interest in the project.
Generated from interconnection queue and public data sources
State
TX
County
Hopkins
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Hopkins Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HOPKNSLR_ALL
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26