Brushy Creek Solar SLF
177.09 MW generation in Tom Green, TX · In queue since January 2019 · Proposed COD June 2028
177.09 MW
Capacity
1
Components
Solar
7y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Brushy Creek Solar SLF is a proposed 177.09 MW solar generation project located in Tom Green County, Texas. The project, developed by Brushy Creek Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-20INR0213, with a queue entry date of January 7, 2019. Its proposed commercial operation date is June 1, 2028, and its interconnection status is currently in the Facility Study phase.
The proposed project consists of 177.09 MW of solar photovoltaic generation. The point of interconnection is the 6444 Red Creek 345kV substation. The Brushy Creek Solar SLF project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Brushy Creek Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6444 Red Creek 345kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- San Angelo Red Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Brushy Creek Solar SLF