Tyson Nick Solar
90.5 MW generation in Lamar, TX · In queue since December 2018 · Proposed COD August 2025
90.5 MW
Capacity
1
Components
Solar
7y 5m
In Queue
IA Executed
IA Status
Signed Aug 2020
Queue → IA
1y 8m
IA → COD
5 years
Total Duration
1y 8m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-08-01
The Tyson Nick Solar project is a proposed 90.5 MW solar generation facility in Lamar County, Texas. The project, developed by Tyson Nick Solar Project, LLC, is interconnected within the ERCOT region under queue ID ERCOT-20INR0222. It entered the queue on December 12, 2018, and has a proposed commercial operation date of August 1, 2025. The project's Interconnection Agreement (IA) was executed on August 28, 2020. The point of interconnection is the 1700 Toco 138kV line.
The proposed project is linked to the existing Tyson Nick operating plant (EIA plant ID 68856). Recent news coverage has highlighted deals and industry aspects related to the project.
Generated from interconnection queue and public data sources
State
TX
County
Lamar
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tyson Nick Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1700 Toco 138kV
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- TOCO_8
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Tyson Nick Solar