Knickerbocker Solar SLF
241.26 MW generation in Tom Green, TX · In queue since January 2019 · Proposed COD June 2027
241.26 MW
Capacity
1
Components
Solar
7y 4m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
8y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
The Knickerbocker Solar SLF project is a proposed 241.26 MW solar generation facility located in Tom Green County, Texas. The project, developed by Knickerbocker Solar LLC, is currently in the ERCOT interconnection queue as entry ERCOT-20INR0235, with a queue entry date of January 7, 2019. The proposed commercial operation date is June 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection (POI) is Tap 345kV 76003 Big Hill - 76009 Twin Buttes. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Tom Green
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Knickerbocker Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 76003 Big Hill - 76009 Twin Buttes
Data Source
LBNL
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Big Hill Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Knickerbocker Solar SLF