New Hickory Solar
209.15 MW generation in Jackson, TX · In queue since January 2019 · Proposed COD July 2026
209.15 MW
Capacity
1
Components
Solar
7y 4m
In Queue
IA Executed
IA Status
Signed Jun 2020
Queue → IA
1y 5m
IA → COD
6y 1m
Total Duration
1y 5m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-07-15
The New Hickory Solar project is a proposed 209.15 MW solar generation facility in Jackson County, Texas. The project, developed by New Hickory Solar LLC, is interconnected within the ERCOT region under queue ID ERCOT-20INR0236. It entered the interconnection queue on January 25, 2019, and has a proposed commercial operation date of July 15, 2026.
The project's Interconnection Agreement (IA) was executed on June 30, 2020, and its current IA status is "IA Executed". The Point of Interconnection (POI) is the OLD_HCKRY_5 bus 5323 345 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Jackson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
New Hickory Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
OLD_HCKRY_5 bus 5323 345 kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.