Voyager Storage
50.14 MW storage in Wharton, TX · In queue since January 2019 · Proposed COD April 2028
50.14 MW
Capacity
1
Components
Battery
7y 4m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
9y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-08
The Voyager Storage project is a proposed 50.14 MW battery energy storage system in Wharton County, Texas. Developed by EDF Renewables Development, Inc., the project consists of 50.14 MW of battery capacity.
The project is currently active in the ERCOT interconnection queue as entry ERCOT-20INR0238, with a queue entry date of January 14, 2019, and a proposed commercial operation date of April 8, 2028. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the 44200 Hillje 345kV substation. The Voyager Storage project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
EDF Renewables Development, Inc.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44200 Hillje 345kV
Data Source
LBNL + Live
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- MEDIUM
- POI Substation
- Hillje Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Voyager Storage